Time table for installation phase available
Posted on 25 Apr 2017 by Wilke
The time table for the installation phase of EMeRGe-EU can be downloaded here.

EMeRGe google calender updated
Posted on 03 Mar 2017 by Vlad
Today the EMeRGe google calender was updated with the latest informations in respect to EMeRGe EU & Asia.

If you dont want to miss anything and/or want to be always up to date, than you can synchronize e.g. calender on your smartphone with the EMeRGe calander.

Topical workshop on 14th - 16th February 2017
Posted on 15 Feb 2017 by Wilke
More than 40 scientists from the EMeRGe community in Germany, Great Britain, China, Japan and Taiwan are participating the topical workshop TEAM: Transport and transformation of pollutants from European and Asian Major population centres.


(click on the image to enlarge)

Read more about the TEAM workshop.

06. Dec. 2016: HALO Flight tests successful
Posted on 22 Dec 2016 by Wilke
The HALO flights required to test the inlet configuration of EMeRGe were successfully carried out.

29. Nov. - 02. Dec. 2016: Second visit to Taiwan to select the HALO basis for EMeRGe in 2018
Posted on 22 Dec 2016 by Wilke
K. Witte and F. Probst (DLR-FX) travelled in the first week of December to fix the location of the hangar for the EMeRGe campaign in Asia. They were again greatly supported by our colleagues in Taiwan (special thanks to Prof. Po-Hsiung Lin, from NTU!) and visited the installations of Air Asia in Tainan, in the Kaohsiung airport, and re-established the contact made at Taichung airport during the previous trip to Taiwan. All the information gathered by DLR-FX concerning hangar, infrastructure and logistics is presently being processed by DLR-FX, which will keep further contact to the corresponding airports in order to select the most suitable option as soon as possible.


14. - 18. Nov. 2016: EMeRGe pre-installation exercise
Posted on 28 Nov 2016 by Wilke
The pre-installation exercise was successfully concluded on the 18th December. The position of the racks for the EMeRGe experimental phases was defined and most of the issues identified for the participant instruments were solved by discussion between the PIs, enviscope GmbH and DLR-FX on the spot. The remaining open issued will be worked out till the end of the year.





14. November 2016: Flight tests
Posted on 28 Nov 2016 by Wilke
The inlet flight tests could not be carried out as initially planned. HALO had a technical problem just before the first flight on Monday and the flight tests had to be postponed. They are now planned for the first two weeks of December 2016.